Episode 173:
Hello and Welcome to the Part3 with me podcast.
The show that helps part 3 students jump-start into their careers as qualified architects and also provides refresher episodes for practising architects. If you would like to show your support for the podcast and help us continue making amazing content, click on the link in the episode notes to sign up to our subscription. I also offer one to one mentoring services to help you with your submissions, exams and interview, head over to our website to learn more or reach out to me on LinkedIn through the Part3 With Me page, or instagram my handle is @part3withme or email me at part3withme@outlook.com.
I am your host Maria Skoutari and this week we will be talking about Acceleration in construction. Todays episode meets PC5 of the Part 3 Criteria.
So when we refer to the term Acceleration within the construction industry, what does this mean and relate to:
When used in connection with construction contracts, acceleration refers to increasing the originally planned or current rate of progress of the work so as to complete the project earlier than would otherwise be the case.
A contractor on a construction project may want to complete the project early in order to reduce site running costs or free up key site staff to work elsewhere. Or they may want to accelerate in order to ensure completion by the contract completion date so as to avoid liability for liquidated damages.
Now on the employers side, they may want a contractor to accelerate progress in order to avoid the construction work being handed over late. In many cases, the completion date for a project is crucial to the employer and any deferment of that date may have very serious repercussions. In these circumstances, it may be in the employer’s best interests to compensate the contractor for any additional costs incurred in accelerating the works, rather than to face the cost consequences of the building not being ready when required and also a claim from the contractor for loss and expense in the form of prolongation costs.
If an acceleration request is issued, what is the process and who would be responsible in reviewing and granting it:
Regardless of the form of contract or type of acceleration agreement, an employer considering acceleration will tend to look to the quantity surveyor to provide advice on the practicalities, risks and costs involved. The Quantity Surveyor will ensure that the quotation includes all necessary details such as the amount of time to be saved, direct costs, consequential losses, and the cost of preparing the quotation.
Now looking at the various building contracts more specifically and which other parties assist with the acceleration agreement assessment:
In any contract type, when preparing an acceleration quotation, the contractor is advised to ensure that it includes a caveat disclaiming liability in the event that further delays are caused by new events that would entitle it to an extension of time. A failure to clarify this point may lead to disagreements and disputes.
Ultimately, however, in any circumstance, the client is the party who decides whether to proceed with acceleration, based on the advice and recommendations made by the quantity surveyor and contract administrator or project manager. The employer's acceptance is formalised through the appropriate contractual mechanism, and any agreement should clearly set out the revised programme, costs, and risk allocations.
Now what happens if a contract doesn’t have an acceleration clause or provision within it:
Under such circumstances, that doesn’t mean that the client can’t ask the contractor to accelerate. Generally under contract law, its always open to the parties to any contract to agree additional or separate contractual terms. Meaning, an acceleration agreement can be drawn up and entered into whether expressly envisaged under the construction contract or not.
Parties will of course need to take into account a wide range of possibilities and permutations and agree who carries the risk of each situation that may arise. If this takes too long to agree between the parties, then they might overrun the acceleration that was intended to avoid, so careful consideration will need to be given for post contract agreement additions.
Let’s move on to how acceleration can be achieved:
Although the standard forms don’t give an indication as to what measures a contractor might consider for inclusion in an acceleration quotation, some possible elements the contractor could consider to improve the rate of progress and which the contractor may be able to change includes:
Now in addition to the changes a contractor could consider to accelerate works, there are also measures the client can make amendments to to enable acceleration, such as:
So once acceleration measures have been assessed by the contractor, they will then put together an acceleration quotation:
Now similarly, to the standard forms not giving an indication as to what measures a contractor might consider for inclusion in an acceleration quotation, they don’t provide any guidance on how a quotation for acceleration should be prepared by the contractor or assessed by the employer. Other than general requirements, such as including all loss and expense, there is no indication given as to what items should be included in the quotation or how those items should be priced.
However, it is clear that, in order to prepare a quotation, a contractor will have to decide what it can achieve, how it can achieve it and how much it will cost.
The decision of what can be achieved is likely to be made by the contractor’s construction or project manager, in conjunction with the site agent and, possibly, the site supervisor and subcontractors. The decision about how to achieve these aims is likely to be made by the construction or project manager and the contractor’s project quantity surveyor. The project quantity surveyor is likely to be the person responsible for applying costs and prices to the decisions made by management.
The main difficulty faced by the contractor when preparing an acceleration quotation is assessing and pricing the risk. Exactly what factors a contractor would take into account when assessing risk will vary from project to project, and the amount of the allowance will depend on commercial considerations and attitude to risk.
If all the risk is to be placed on the contractor, it may be better for a lump sum quotation to be provided, although this will make it difficult for the client to assess the merits of the quotation. It may be that the client is far less concerned about whether individual elements of the contractor’s quotation appear to be high and more about whether the money that can be saved by completing early justifies the money that will have to be spent on acceleration. If the client wants as low a quotation as possible and is prepared to accept the risk of failure to achieve an early completion date, it will be more important for a detailed price breakdown to be obtained from the contractor.
Although the standard forms of contract envisage a quotation being provided before an acceleration agreement is made, the parties may agree to value acceleration measures on the basis of costs actually incurred. If an assessment is to be made on the basis of actual cost, the client will not know the additional cost they will have to pay out until after the measures have been put in place and the costs expended. In this case, the client will have to base their decision on an estimate of the likely cost of acceleration.
Something clients must always be wary of when it comes to acceleration, is an implied instruction to accelerate:
If a client is under severe pressure to have construction work completed by a particular date, they may occasionally tell contractors that the project must be completed and handed over by the completion date come what may. In such instances, the contractor may point to the extension of time clause in the contract, but a client who is under pressure may be extremely resistant to grant an extension of time and may try to impress onto the contractor the imperative to finish by the specified dates, regardless of any additional cost. It can be argued that a statement like this can be deemed as an implied instruction to accelerate. If a contractor thinks it is being asked to take action to accelerate the works, it would be well advised to clarify the situation rather than to take action in the belief that additional costs will be reimbursed. Equally, professional advisers to an employer making a statement like this ought to seek to clarify the situation.
So factors that should be considered when suggesting and agreeing acceleration measures, should include:
The building contract it is relevant to, for example, in NEC contracts, the programme is an integral contract document, whereas this is not typically the case under the JCT. Also, most contracts will require specific instructions to be given to make changes to the work, or the conditions under which it is to be carried out, while some require the express permission of the contractor to omit parts of the work.
One general point, which applies to any acceleration measure, is that the changes must be focused on activities that are critical to completion. If the progress of a particular activity is expedited, it will only bring forward the overall completion date if it is an activity that is on the critical path of the programme.
Additionally, cost may be a prohibiting factor, as the initial costs provided for the works from the contractor would have been based on optimum levels of resources and adopting efficient procedures and methodologies, changing these as part of the acceleration quotation will create an imbalance or loss of efficiency. When an acceleration agreement has been reached, it is important that the parties make a careful and accurate record of progress achieved at the date when acceleration commences.
As such, decisions regarding acceleration should be based on a thorough cost-benefit analysis, considering various risks and potential outcomes.
To sum up what I discussed today: